Ongoing Projects

SinomaBeni Suef 6*6000TPD Clinker Cement Project (CDR)

IMG_4923

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

Beni Suef

Chengdu Design & Research Institute of Building Materials Industry Co., Ltd.

214,000,000

Industrial

Civil Works

July 01, 2017

0 %

SinomaGOE Arish Cement Plant Phase 2

DSC00858

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

Arish

Government of Egypt (Main Contractor: Sinoma CDRI)

209,000,000

Industrial

Civil Works

August 30, 2016

97 %

Emaar-logoMIVIDA-PK#80 PARCEL 19

1

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

New Cairo

Emaar

196,495,245

Real Estate

Civil, MEP & Finishing

August 15, 2018

5 %

cairo_foCFC Oriana Villas [Phase 3]

DSC_0019

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

Cairo 5th District

Al Futtaim Residential Resorts Development S.A.E (AFRRD)

122,721,725

Real Estate

Civil, MEP & Finishing

July 15, 2017

28 %

Edita E08 Factory  edita-logo

Untitled-1

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

6th of October City

Edita Food Industries S.A.E

116,000,000

Industrial

Civil & MEP

January 16, 2017

11 %

The Polygon [Phase 3]

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

6th of October City

Sodic

110,731,290

Commercial Building

Civil Works

July 01, 2017

0%

maintenance_engineeringHangar 7000

20160427_173734

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

Cairo

Egypt Air Maintenance & Engineering

98,000,000

Air Port

Civil, MEP & Arch

January 01, 2017

85 %

Zayan Center

IMG-20160512-WA0008

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

Alexandria

Hamdy Abdel Fatah Zayan

93,700,000

Commercial Building

Civil Works

September 16, 2016

95 %

Bonjorno Factory Buildingbonjorno

5

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

6th of October City

Caravan Marketing Company

91,000,000

Industrial

Civil & MEP

September 10, 2016

25 %

Henkel Change Civil Construction [Phase 2]

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

6th of October City

HENKEL

78,000,000

Industrial

MEP

March 01, 2017

0%

Unilever Mashreq Factory unilever2

Renovation & Refurnishing

DSC_0064

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

6th of October City

Unilever

74,124,318

Industrial

Civil & MEP

August 16, 2016

96 %

Carrefour Mall of Egypt

DSC_0312

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

6th of October City

MAF For Installations and Management of Hypermarkets

67,200,000

Retail

Civil, MEP & Finishing

August 30, 2016

80 %

SinomaSVCC Clinker Grinding Plant

Picture1

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

Beni Suef

Sinoma CDI

53,389,725

Industrial

Civil Works

January 01, 2017

11 %

MIVIDA-PK071
Parcel 49 FM Building

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

New Cairo

Emaar Misr

48,873,119

Real Estate

Supply & Installation of Civil, Finishing & MEP

January 01, 2017

2%

triTriangle Building Office

20141208_102211

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

Katamya

Triangle Group

45,000,000

Administration Building

Civil, Arch & MEP

December 28, 2016

50 %

Henkel [New Liquid Plant]

Full page photo

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

6th of October City

HENKEL

34,450,000

Industrial

Civil & Steel Structure Works

September 15, 2016

25%

cirBadr 500/220 KV GIS Substation

20160106_113027

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

Badr City

General Electric

28,000,000

Power

Civil & MEP

August 28, 2016

95 %

Qena Cement and Coal Mil
Factory

Picture1

Location

Client

Contract Value L.E.

Type of Construction

Type of work

Date of Completion

Percentage Complete %

Qena

MISR Cement Co. Qena

12,100,000

Industrial

Civil & MEP

January 01, 2017

5%