GOE Coal Grinding

2016-05-17 08.19.56
2016-05-17 08.20.35
2016-05-17 14.28.04
  • Client: Sinoma [TCDR]
  • Project Location: Arish, Egypt
  • Consultant: TCDR
  • Project Duration: 10 Months
  • Start date: October 2015

Project Description:

Coal Storage Main workshop( include windbreak foundation) Convey & transfer station (include coat bin) First Coal Mill, 2nd Coal Mill, Coal Mill substation (2) Storage Substation, Compress Air Station.

Main Items:

Civil Works